Rotherhithe Theatre Project Manual

Version 1.4 (Integrated) — December 6, 2025
Status: Publication-ready guidance (integrated with Rotherhithe 2 site report)

Table of Contents

  • Front Matter: Purpose, audience, golden thread, versioning
  • Part 1 — Foundation & Framework
    • • Strategic purpose and scope
    • • Three-phase lifecycle (Discovery → Implementation → Closure)
    • • Governance and risk profile
    • • Stakeholders, roles, and RACI anchors
    • • Compliance baseline
  • Part 2 — Core Project Phases
    • • Discovery: site selection, feasibility, funding triggers, decision gates
    • • Implementation: design/permissions, build/fit-out, operations ramp-up
    • • Closure: demobilisation, handback, learning capture
  • Part 3 — Site Pathways & Case Studies
    • • Site A: Lavender Pumphouse (350-seat community theatre hub)
    • • Site B: Brunel Tunnel Shaft (100-seat subterranean niche venue)
    • • Site C: Printworks / Harmsworth Quays (large-scale cultural anchor)
  • Part 4 — Specialist Guidance
    • • Heritage and consents (Scheduled Monument, listed fabric)
    • • Transport and crowd management (including rail adjacency)
    • • Safety and licensing (CDM, H&S, Premises Licence/TENs)
    • • Financial model and funding bodies by phase
  • Part 5 — Tools, Tables, and Templates
    • • Site screening matrix; viability decision gates; budget structure
    • • Risk register; stakeholder matrix; programme milestones
    • • Checklists (week 1, day-by-day, phase gates)
  • Part 6 — Appendices
    • • Glossary; references; update log; quick reference charts

Golden Thread

DiscoveryImplementationClosure

With explicit decision gates, risk ownership, and evidence trails that satisfy planning authorities, Network Rail Asset Protection, heritage bodies, insurers, and funders.

Key Phases

Discovery

Duration: 3–6 months
Cost: £5k–£15k

  • • Low-cost feasibility
  • • Avoid premature capital spend
  • • Set risk profile
  • • Decision gate: Go/No-Go

Implementation

Duration: 12–24 months
Cost: £100k–£2m+

  • • Design & permissions
  • • Build & fit-out
  • • Enact controls
  • • Decision gate: Ready to operate

Closure

Duration: 2–4 weeks
Cost: £5k–£15k

  • • Demobilise safely
  • • Protect reputation
  • • Capture learning
  • • Project complete

Compliance Baseline

Minimum mandatory controls across all projects:

DomainBaseline Controls
Rail AdjacencyAPA application; 2.4m boundary; daily inspections; incident hotline
HeritageNo intrusive works without consent; reversible fittings; conservation-approved fixings
H&S / CDMPrincipal Designer/Contractor; CDM Plan; RAMS; confined space plans
LicensingPremises Licence/TENs; capacity sign-off; stewarding; noise management
AccessibilityStep-free where feasible; mitigations if not; clear disclosures

For the complete manual, visit Resources to access the full PDF document.